TERMINAL APRON PAVEMENT EVALUATION AND REHABILITATION PROGRAM ROBERT MUELLER MUNICIPAL AIRPORT

LOCATION:  AUSTIN, TX

CLIENT:  CITY OF AUSTIN

CONSTRUCTION COST: $772,000

 

Engineering services included structural evaluation and rehabilitation design for the Terminal Apron pavement at Robert Mueller Municipal Airport. The Preliminary Design Phase of the project completed in August 1989, included field data collection, pavement analysis and evaluation, analysis of rehabilitation alternatives, and recommendation of a rehabilitation strategy. The Design Phase, completed in April 1990, included the preparation of construction plans, specifications, and cost estimates for the recommended rehabilitation alternative.  Bidding and construction phase services were also provided.

 